Update, Wednesday, November 4, 2026:  Street Sweeping will resume effective Wednesday, November 11, 2026. 

Update:  Tuesday, October 27, 2026: DUE TO ONGOING CONSTRUCTION THERE WILL BE NO STREET SWEEPING ON WEDNESDAY, OCTOBER 28TH.

Update:  Thursday, October 15, 2026:

Allegheny County’s miiling contractor, Folino Construction, plans to complete work on Thursday, October 15, 2026 (today).

Allegheny County’s in-house paving crew anticipates paving on Grand Avenue will start on Monday, October 19 or Tuesday, October 20, 2026.  The start date depends on weather.  The County’s goal is to complete paving on Grand Avenue in less than three weeks.

During paving, the work zone will move up and down the road, and at the work zone, traffic will alternate and will be controlled using flaggers. Drivers should expect to experience delays.

Please use extreme caution to protect workers,pedestrians and drivers in the work zone.

The County thanks you for your patience and understanding while we complete this project as quickly as possible.

Neville Township will suspend Street Sweeping during milling and paving operations and parking WILL be permitted on local, side streets.

************

Update:  Friday, October 10, 2026 – The following post has been updated to reflect a revised start date of MONDAY, OCTOBER 12, 2026 due to weather delays.  Streetsweeping  will not occur on WEDNESDAY, OCTOBER 14, 2026 and parking WILL be permitted on local, side streets.

Update:  Tuesday, September 29, 2029 – The following post has been updated to reflect a revised start date of Wednesday, October 7, 2026 due to weather delays.  Streetweeping will proceed as scheduled on Wednesday, September 30th.  There will be no streetweeping on Wednesday, October 7th.

Original Post – Thursday, September 17, 2026 with edited dates

Allegheny County Public Works expects its contractor, Folino Construction, to mill Grand Avenue between the Coraopolis Bridge and Neville Road (at VFD Station 205) in Neville Township starting on MONDAY, OCTOBER 12, 2026

The milling work will occur between 6 a.m. and 6 p.m. on weekdays, weather permitting, and it is expected to take 5-6 days.

The work zone will move up and down the road. At the work zone, traffic will alternate and will be controlled using flaggers. Drivers should expect to experience delays at/near our work zone.

Road paving is anticipated to start as soon as the milling work is done, and the County’s in-house paving crew has finished work another road. Anticipated paving start date – during the week of October 12 – weather and other factors may alter the paving schedule.

Neville Township will suspend Street Sweeping during millng and paving operations and parking WILL be permitted on local, side streets.